Your project is behind schedule due to conflict between team members .Haring resolved the conflict, to get the project back on schedule,you should consider
( )
.
A.
crashing the Schedule
B.
performing resource leveling
C.
conducting reverse resource allocation Scheduling
D.
utilizing the critical chair resources